St Edmund Lodge No 4714 CALNE Province of Wiltshire
|
![]() |
Building in progress
Sunday 6th April 2008
The building framework is now completed.
Wednesday 9th April 2008

The base layer of bricks are being laid. These will contain the concrete flooring when cement is fully cured.

9th April - WM Elect visits site. Bob will be first WM in the new lodge.
15th April - Footings laid and underfloor pipe laying in progress. Almost ready for the concrete to be poured.